New Clark airport terminal 87.6% complete

News

The Department of Transportation (DOTs) has revealed that the new Passenger Terminal Building (PTB) of Clark International Airport is now at 87.61% completion.

DOTr said that the construction of the main terminal building, utility building, and ancillary facilities are ongoing and in various stages of completion.

“Landside works are also being accelerated, which include the terminal forecourt, elevated road, main access road, secondary access road, passenger car park, employee car park, rental car park, taxi buffer area, bus station, and vehicle control post,” DOTr said.

The new Clark International Airport PTB is projected to be completed by mid-2020. It is expected to boost the airport’s operational capacity from 4.2 million passengers to 12.2 million passengers annually.

“The expansion will significantly improve air connectivity in Luzon, and help ease decongestion at the Ninoy Aquino International Airport (NAIA),” DOTr said.